People in Thu Duc City are suffering when going to Vo Van Ngan street because of the contractor’s delay

by worldysnews
0 comment

Thu Duc City Project Management Board said that the delay in implementing the project on Vo Van Ngan Street had subjective reasons such as the contractor’s procrastination, sluggish construction, and continuous violation of schedule.

Recently, newspaper Dan Tri There has been a review article about this. Accordingly, this road is only about 2km long but there are dozens of meters of construction blockhouses located in the middle of the road, making people’s travel difficult.

Regarding this content, the Construction Investment Project Management Board of Thu Duc City (Thu Duc City Project Management Board), said that the Dang Van Ngan route from Dang Van Bi street to Thu Duc market was constructed by a contractor. Drainage system (box sewer) in the middle of the road. However, the construction progress on the above road section is very slow, affecting traffic and people’s lives.

Construction progress on Vo Van Ngan street is delayed, affecting people’s circulation (Photo: Nam Anh).

Thu Duc City Project Management Board also frankly pointed out that the subjective reason was that the construction contractor was sluggish, did not organize the construction sluggishly, did not proactively speed up the progress, and continuously violated the schedule. This unit also affects traffic safety, environmental sanitation, and affects people’s daily life, business, and commerce during construction.

In particular, the delay in construction has caused public outrage and anger and seriously affected the investment efficiency of the project.

Therefore, Thu Duc City Project Management Board reported to the Department of Construction and Thu Duc City People’s Committee that the above contractor violated progress, breached the contract and terminated the contract. Currently, the project has completed about 50% of the work volume.

People in Thu Duc City suffer when going to Vo Van Ngan street because of the contractor's delay - 2

The construction area on Vo Van Ngan street causes environmental unsanitary and dusty (Photo: Nam Anh).

Recently, Thu Duc City Project Management Board also organized a bidding to select contractors to complete the remaining items of the project through the national bidding network system. Currently, the project has a new contractor and focuses on speeding up the construction progress of sidewalks, drainage systems and remaining items.

Regarding objective reasons, Thu Duc City Project Management Board said that the box culvert of this project is large in size and needs to be dug deep while the area’s geology is weak. The construction area is located in the middle of the road, while the large volume of vehicles has affected traffic.

On the other hand, this place has steep terrain. When it rains and the water flows rapidly, the contractor will waste time pumping water and re-treating the excavation site. During the construction process, the units also encountered technical infrastructure projects such as electric cables, water supply pipes, and telecommunications cables, and spent a lot of time coordinating surveys and agreeing on plans.