Hanoi City Inspectorate pointed out the responsibility of departments and branches for slow determination of land prices in 10 projects

by worldysnews
0 comment

Urgently have a written response to the petition of the Vietnam Appraisal and Appraisal Company for the Office and Commercial Service Building Project at Lot C/D11, Cau Giay New Urban Area, Dich Vong Hau Ward , Cau Giay District).

At the same time, request VIC Investment and Valuation Joint Stock Company to urgently and seriously review and complete the Land Valuation Certificate; In case the consulting unit is still slow in implementation, the Department of Natural Resources and Environment reports and proposes to the City People’s Committee to take handling measures according to regulations for the Dich Vong New Urban Area Project, Cau Giay District.

Request IVC Vietnam Valuation Joint Stock Company to urgently review and issue a Land Valuation Certificate to continue implementing the next land price determination process as a basis for submitting to the City People’s Committee for approval of specific land prices according to regulations for the project to build headquarters and offices for rent, Yen Hoa ward, Cau Giay district.

Urging the People’s Committee of Cau Giay district; instruct Tu Liem Urban Development Joint Stock Company to urgently implement the contents as requested by the Department of Natural Resources and Environment in Document No. 4434/STNMT-KTĐ dated June 19, 2023. On that basis, the Department of Natural Resources and Environment urgently carries out the process of determining the next land price as a basis for submitting to the City People’s Committee for approval of specific land prices according to regulations for the Dich Vong New Urban Area Project, Cau Giay District.

For the Department of Finance, it is necessary to learn from the delay in organizing meetings and reviewing plans, leading to the issuance of a document requesting the Department of Natural Resources and Environment and the consulting unit to review the slowness of 04 projects (Projects). Construction investment project, operation and business of an office complex for rent at 289 Khuat Duy Tien, Trung Hoa ward, Cau Giay district; Project of mixed commercial service building, office, hotel in Mai Dich ward, Cau Giay district; Dich Vong Urban Area Project, Cau Giay District; Project to build headquarters and offices for rent, Yen Hoa ward, Cau Giay district).

Assign the Department of Natural Resources and Environment and the Department of Finance to urgently advise the City Specific Land Price Appraisal Council and the City People’s Committee to issue a decision approving the land price plan according to regulations for 03 projects (Project of Mixed-use Service Building). commercial services, offices, hotels, Mai Dich ward, Cau Giay district; Office and commercial service building project at Lot C/D11, Cau Giay new urban area, Dich Vong Hau ward, Cau Giay district ; Housinco Tan Trieu office and housing complex project at plot CT5, Southwest Kim Giang I new urban area, Tan Trieu commune, Thanh Tri district).

Assign the Department of Construction to organize a review of the responsibilities of collectives and individuals in the slow implementation of reviewing and giving comments on documents of the Department of Natural Resources and Environment as a basis for determining specific land prices in Construction investment project of Son Loc housing area, Son Tay town.

Assign Cau Giay District People’s Committee to coordinate with the Investor to determine the current land use status, compliance with land laws and site clearance results as a basis for reporting to the Department of Natural Resources and Environment as a basis for determining additional financial obligations of Dich Vong Urban Area Project, Cau Giay District.

Hanoi People’s Committee has also issued a document directing the implementation of the Inspection Conclusion on the delay in determining specific land prices as a basis for calculating land use fees and land rent; Accordingly, consistent with the Inspection Conclusions of the City Inspectorate, request units to seriously implement; assign the City Inspectorate to monitor, urge and inspect the implementation of the Conclusion according to regulations and synthesize and report to the Chairman of the Hanoi People’s Committee on the results of implementation.