Which is in Petrobangla’s 100 day plan – 2024-02-14 05:17:36

Petrobangla has formulated a 100-day action plan of the government with emphasis on domestic gas exploration. The government ordered to formulate a 100-day action plan after taking charge. Already the most important organizations of energy department have submitted 100 days action plan to energy department.

A copy of the plan has been obtained by the Bengali Tribune. In addition to gas, it has also been informed that decisions should be taken to extract coal.

digging a well

Petrobangla plans to contract with three multinational companies to drill gas wells within the next 100 days. These three companies are Sinopac, Gazprom and Ariel.

Petrobangla Chairman Janendra Nath Sarkar says in his plan, the government will drill 46 wells by 2025. These three companies have been selected to drill 17 wells.

BAPEX usually drills most of the wells in the country. But due to the emphasis of the government on domestic energy, more wells have to be dug simultaneously. It is not possible for Bapex alone to drill this well. For this, new wells are being dug with foreign contractors.

The government plans to drill a total of 48 wells by 2025. Four of these wells will be drilled at greater depth. That is deep drilling. Deep in the soil are hard rocks. What lies underground through these rocks is yet to be seen in the country. Experts believe that drilling these four new wells will reveal what lies in that layer.

Apart from drilling wells, they will look at annual well drilling, estimated gas recovery, feasibility survey of various projects and formulation of DPP.

READ Also:  Squad Busters, a mobile video game, has already been released; of this about

Pipeline construction

Securing funds for land acquisition for the construction of Bakhrabad-Meghnaghat-Haripur pipeline, appointing consultants to prepare the pipeline master plan, obtaining government approval for the construction of 295 km high pressure 52 inch diameter pipeline from Maheshkhali-Matarbari, trying to get funds from donors for the construction of various pipelines of GTCL, Shajabazpur And it is planned to finalize the feasibility of constructing the pipeline from Bhola North to Barisal.

Construction and importation of LNG terminals

Finalization of site for construction of Cox’s Bazar Matarbari permanent terminal, Finalization of draft agreement with Age Energy for LNG import from India, Draft agreement signed with Summit for construction of third floating terminal at Maheshkhali, Signing of a separate draft agreement with Summit for long-term LNG import, for long-term LNG import. Draft agreement with Perrentis Malaysia to be finalised.

Prepaid meter

For Titus Gas, 1.1 million through the World Bank, 6.5 million by ADB, and 1.28 thousand by the Western Gas Distribution Company will be appointed as consultants for the installation of prepaid meters.

Mining

In-principle approvals for coal mining from Barapukuria expansion area and expansion of Madhyapara hard rock project are planned.

Consent to bring gas from Jokiganj to CNG

After Bhola, now it is being thought to bring gas from Jokiganj in Sylhet using CNG. The Ministry of Power, Energy and Mineral Resources intends to implement the project under the Special Act 2010.

When asked about this, Petrobangla Director (Operation) Md. Kamruzzaman told Bangla Tribune, after the formation of the government, we were instructed to plan for 100 days. We have formulated and submitted a plan with everyone’s input. I will start working now. Among these, some work is already underway, we will take it forward.