After complying with the city’s sanctions, the investor consortium issued an official dispatch requesting to extend the progress of the Social Housing project in plot NO1. Thereby, it is proposed to start construction in the fourth quarter of 2024.
Recently, the People’s Committee of Hanoi City issued a Decision to sanction administrative violations regarding the delay in implementing investment in social housing construction on land funds reserved for social housing development according to regulations in the Urban Area Project. Ha Dinh new town on the land area of Tan Trieu commune, Thanh Tri district, Hanoi city. With a fine of 140 million VND. At the same time, businesses are required to start construction on social housing projects within 30 days from the date of signing the sanctioning decision.
It is known that the social housing project at land lot No1 in Ha Dinh urban area was assigned by the Hanoi People’s Committee to the joint venture of Hanoi Electricity and Water Equipment Construction Joint Stock Company – Haweicco, Infrastructure Investment and Development Corporation. UDIC urban floor – One Member Company Limited and DAC Hanoi Housing Development Joint Stock Company are the investors in Decision No. 2784/QD-UBND dated June 26, 2020 with the project implementation schedule being: investment preparation period from the third quarter of 2020 to the second quarter of 2021; investment implementation period from the third quarter of 2021 to the third quarter of 2022; The investment phase will end and be put into operation and use from the third quarter of 2022. According to the agreement between the parties in the joint venture, UDIC Corporation (a 100% state-owned enterprise) is the joint venture representative.
Please extend the implementation time
The representative of the investor consortium said that the slow implementation of the project was due to a number of objective reasons such as planning adjustments, leading to extended time to carry out procedures.
Specifically, on November 1, 2022, the City People’s Committee issued Decision No. 4185/QD-UBND on approving the investment policy adjustment. In the Decision, in addition to the content adjusting the project scale, the implementation schedule is adjusted as follows: construction starts in the fourth quarter of 2022, completed in the third quarter of 2024.
Social housing project in plot NO1, Ha Dinh urban area
In addition, because the project has up to 60% capital of state-owned enterprises (contributed capital of UDIC Corporation), the management and use of state capital invested in production and business of the project in addition to implementing According to general regulations, at the same time, we must ensure compliance with the provisions of the Law on Management and Use of State Capital Invested in Production and Business at Enterprises, the Land Law, the Investment Law, and the Construction Law. ,… as well as Decree No. 10/2019/ND-CP on exercising the rights and responsibilities of the State owner’s representative… Therefore, the investor partnership needs time to complete the procedures according to regulations. determined.
Outside the social housing project in plot NO1, Ha Dinh urban area
Next, due to the transition from QCVN 06:2021/BXD to QCVN 06:2022/BXD, the fire protection approval time for the project was extended.
The representative of the joint venture said that immediately after receiving the penalty decision, on February 7, 2024, the investor joint venture complied with paying the fine according to the city’s decision and urgently prepared the necessary procedures. construction investment procedures such as: there has been a decision to approve the project, approval of the contractor selection plan, approval of the construction drawing design of the experimental pile item, and submission of documents for fire protection approval. Construction drawing design stage for the Fire Police Department, preparing construction drawing design documents and estimates to serve the construction permit application step.
After complying with the city’s sanctions, on March 16, 2024, the investor consortium sent an official dispatch to the Hanoi People’s Committee requesting to extend the progress of the Social Housing project in plot NO1. . The Investor Joint Venture proposed to start construction in the fourth quarter of 2024.
Tran Hoang